April 20, 2009
Outokumpu Stainless contract well underway
Our contract as CDM Co-ordinators at Outokumpu is now well underway with EDS having desheeted the building and now demolishing the racking systems with the help of the 777 Demolition super long reach machine.
As you can see from the photographs the machine size and reach allows it to safely remove the racking piecemeal style and work along the building from the gable end.
EDS supervisor Tommy Swift is on programme to complete the works as the original estimated duration and we will post additional photographs throughout the contract.
Les Hemmings is dealing with the project on a day to day basis with John Woodward visiting site once a month.