September 28, 2015

Total Reclaims is working 120 feet in the sky


The Nottingham Post recently featured work on Lenton Flats by C&D customer Total Reclaims Limited. The job requires scaling 16 flights of scaffolding stairs in order to reach the top, some 120 feet in the air.

So far four floors have been removed using electro-hydraulic breaker Brokks. One floor is dismantled at a time, and one concrete panel at a time. The flats were 17 storeys tall, but Total Reclaims has got that down to 13 in just 8 weeks. When they reach 11, then the Brokks work stops and a 360 excavator with a 35 metre reach takes over to demolish the rest.



Source: Nottingham Post