Tallest concrete structure ever demolished is coming down on September 7th in Kent


Contractor Brown & Mason is set to go into the history books next Wednesday when it implodes the chimney at Grain Power Station in Kent. Standing at 244 meters tall, it's two-and-a-half times taller than Big Ben and taller than 55 stacked double-decker buses. It's basically really really tall.

The site is owned by energy company Uniper who intends to turn the old power station into a new, 1,275MW gas-fired modern power station. So far 5 demolition contracts have been carried out to clear the site, with the chimney implosion being the 6th. In total, 84,000 tons of material has been removed and recycled.

Source: Kent News

November 3, 2014

Congratulations to our friend Mick Williams who has moved from Keltbray to Brown and Mason


Mick Williams is one of the UK's most well-known and experienced explosive demolition engineers, and he has recently completed a move from Keltbray over to demolition, dismantling, and decommissioning company Brown and Mason (BAM).

Our friend Mick has over 750 blasts to his name, both in the UK and further afield, and has accrued more than20 years working in the business. That total will surely surpass 800 blasts before long with BAM having between 20-25 blasting jobs scheduled over the next 2 years. And that's partly why Mick has joined BAM. He enjoyed his time at Keltbray, but they don't have much blasting work planned in the near future.

Expect to see Mick's expertise at work almost immediately on BAM's current work schedule including our power stations at Kingsnorth, Isle of Grain, Teesside and Cockenzie, and at Coryton oil refinery.

Source: Demolition News

December 17, 2013

Cockenzie Power Station's first two structures will be imploded today


The Cockenzie Power Station is set to be demolished, with today being the day that the two 34-metre high and 300-tonne steel precipitator structures are being imploded as part of an 18-month job to completely remove the station from the site.

The controlled explosion is set to happen at 2pm today by specialists Brown and Mason. Once down, a further 14 precipitator structures remain and will also face implosion. However, the most exciting part of the demolition is yet to come. Those two chimneys you see in the image above are also set to be demolished, but not until early next year.

There's no date set for the chimneys to come down yet, but it might be an event you want to attend. They are a local landmark having stood for 45 years, and this will clearly change the skyline forever.

Source: Edinburgh News