DDS Demolition case study video for the Fast Ferry Berth Demolition
The video above is a case study produced by C&D customer DDS Demolition about their demolition of the former fast ferry berth infrastructure at the Dover Western Docks.
The job started in April of last year and was a 4 month job, which eventually took 6,184 man hours with no accidents incurred. The recycle rate for the project was an impressive 98%.
You can read full details about the contract over on the DDS Demolition website.